Download document () of 20

One-stop approach to project coordination

Eaton provided a one-stop approach to coordinate two utility providers and incorporate existing generation into expanded substation capacity for a large food grower’s expansion.

Summary: Bolster power distribution capabilities to accommodate rapid greenhouse expansion

Challenge
The company was expanding and needed a new power distribution system, incorporating existing generation and meeting requirements of two separate utilities providers.
Solution
Results
Coordinated with utility providers while providing a cost-effective power distribution system, meeting current and future needs.

“Eaton served as a single point of contact for the customer, coordinating everything from working with in-house engineering and construction managers and holding discussions with the IoUs to the installation and commissioning of the overall power distribution system."

Greenhouse customer, Northeast, US

Challenge: Expanded electrical needs for greenhouse expansion

While the greenhouse expansion and new greenhouse construction project were in the same vicinity, they were under the jurisdiction of two different Investor-owned Utilities (IoUs). This posed a major execution challenge for the overall substation design, since the priorities and overall project approach differed. For example, one utility wanted to build a switching station onsite and feed the connection to the greenhouse, a task that required intensive coordination between Eaton and the utility to ensure the interconnection requirements of the transformers, conduits, etc. were met. 

A key challenge faced in the project was utilizing the existing natural gas-fired generator, which necessitated that the switchgear parallel the generator. This required incorporating different relays and controls to monitor, synchronize and have an effective tradeoff between the utility connection and the generator—the customer would use the generator when the cost of the utility’s electricity was more than the cost of natural gas, to maximize cost savings.

Substation design project

Solution: Eaton project management

Eaton worked on two separate projects for the customer: a brownfield/expansion project followed by a greenfield/new construction project. The projects had some similarities, since Eaton undertook the design, equipment procurement, installation and commissioning for both, and the solution provided was a 35 kV / 13.8 kV / 400 VAC distribution system. However, the projects were completed for two different utility territories, had different existing installed equipment and interconnection requirements. Eaton's turnkey experience working with the utility market played a key role in the successful execution of both projects.
Engineers in substation

Eaton’s experience working with the utility market played a key role in the successful execution of both projects; the presence of two different utility providers resulted in significant alteration in the solution’s workflow and deployment.

Project Manager, Eaton

Results: Successful greenhouse expansion

The customer’s continued engagement with Eaton on the greenfield greenhouse project was a testament to Eaton’s successful delivery of the initial greenhouse expansion project and the value-add provided, including:

  • IoU: Eaton leveraged relationships and expertise with electric utility providers and knowledge of codes and standards to ensure all controls were properly installed and the interconnection requirements were successfully met.
  • Low maintenance requirement: Eaton designed a solution that significantly minimized the need for regular maintenance. The complexity of the system was reduced by avoiding the use of switches, alarms, etc. and instead used a direct burial cable and unit substations with medium voltage fuses that are significantly easier for the customer to operate and maintain.
  • Faster deployment and sustainability: Eaton met the customer’s aggressive timeframe, successfully executing the project in 6-8 months, quicker than the industry average. This was possible due to a design-build approach, enabling expedited delivery of equipment. 
Men looking at substation

Eaton’s end-to-end involvement in the project highlighted its “one-stop shop” approach that included coordinating with two utilities and providing a cost-effective, best-in-class power distribution system that meets the customer’s needs—today and in the future.

Project Manager, Eaton